The purpose of this page is to document any tasks that need doing on a specific date or time. A typical pending task might be a small piece of mid-cycle work to finalise the installation & commissioning of a device on an instrument. Use the table below to add new pending tasks. When the task is done, it can be removed from the list.

Date Required Instrument
/Area
Description Ticket Assign To
Summer Shutdown EMMA-A Test new galil driver #2830
After cycle VESUVIO Update mode and offset. #3210 Alistair
09/08/2019 ALL Create IBEX 5.5 Release #4422
16/08/2019 ALL Deploy IBEX 5.5 Release #4423
Shutdown MERLIN TPG300 #4395
Shutdown MERLIN, MARI, LET Add ISISDAE_01__ISISDAE_MAX_NTC=30000 to globals.txt #4496 Tom
12-16 Aug TS2 Chilled water off, power down as much equipment as possible in A/C rooms