There are some legitimate cases where a split is possible by the algorithm, even with this parameter set to false. You would need to run with the parameter "plan.loglevel" set to 9 to understand why it's splitting the requirement in multiple parts. |
Beta Was this translation helpful? Give feedback.
-
Not that easy to interpret the frepple log files.
This section indicates that it's related to capacity. Only 30 units fit within the available time slot of capacity. If the operation wouldn't have been an alternate with MINPENALTY criterium, I think the demand would have stayed in 1 MO. Try leaving the priority and search_mode fields of operation 236 blank. |
Beta Was this translation helpful? Give feedback.
-
Hello everyone,
I have a sales order for an item with an operation defined exclusively for it. It has no other dependent operations, and the system generates two consecutive work orders in time.
This shouldn't happen if the option to allow splitting sales orders into multiple orders is set to "false," and it also doesn't make much sense to split the orders and place them one after the other.