A more balanced usage of your resources isn't too difficult to configure: a) Use "minpenalty" als search mode, and b) assure the resource cost field is different from 0. |
Beta Was this translation helpful? Give feedback.
-
Try setting the parameter plan.loglevel to 2 and check out how the algorithm evaluates each of the alternatives. |
Beta Was this translation helpful? Give feedback.
-
You should read up on Theory Of Constraints The plan should follow the pace of the bottleneck resource (what you call "most crowded one"). The rest of the plan should be centered around the bottleneck.
You can build in safety time in your schedule with the "post operation time" field of the operation. |
Beta Was this translation helpful? Give feedback.
-
Hello,
Is it possible to schedule the operations equally between operation resources? I have tried to change the search mode for operationresource to variate things, but it seems that everything is scheduled for the first resource option, if the item is possible to make on time.
What I really would like to do is to have the tasks scheduled as tight as possible using all available resources and not mind them being early.
Thanks!
Beta Was this translation helpful? Give feedback.