You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
This is not a big deal because not many analyses include a lot of existing Generator and PV and O&M cost is often not a huge cost driver on total lifecycle cost, but:
Update optimization to only apply 3rd-party factor to newly-sized kW for O&M costs. Existing technology O&M costs should have offtaker PWF and tax factors applied to it.
We've updated the calcs in proforma.jl to be this way, but the optimization lumps existing Generator and PV O&M into the developers costs.
The text was updated successfully, but these errors were encountered:
This is not a big deal because not many analyses include a lot of existing Generator and PV and O&M cost is often not a huge cost driver on total lifecycle cost, but:
Update optimization to only apply 3rd-party factor to newly-sized kW for O&M costs. Existing technology O&M costs should have offtaker PWF and tax factors applied to it.
We've updated the calcs in proforma.jl to be this way, but the optimization lumps existing Generator and PV O&M into the developers costs.
The text was updated successfully, but these errors were encountered: