This proposal is a risk parameters update by Gauntlet, primarily setting supply and borrow caps in assets listed on Aave v2 and v3 Polygon.
Transaction: https://etherscan.io/tx/0xce32499bdc4f1c5707e20b29d33627717cebe7fe0fff1282ee93b227123801c9
- id: 112
- creator: 0x683a4f9915d6216f73d6df50151725036bd26c02
- executor: 0xee56e2b3d491590b5b31738cc34d5232f378a8d5
- targets: [0x158a6bc04f0828318821bae797f50b0a1299d45b,0x158a6bc04f0828318821bae797f50b0a1299d45b]
- values: [0,0]
- signatures: [execute(address),execute(address)]
- calldatas: [0x00000000000000000000000003232b5ee80369a88620615f8328beec1884b731,0x0000000000000000000000004393277b02ef3ca293990a772b7160a8c76f2443]
- withDelegatecalls: [true,true]
- startBlock: 15799327
- endBlock: 15818527
- strategy: 0xb7e383ef9b1e9189fc0f71fb30af8aa14377429e
- ipfsHash: 0x854fbd7bfa7e8d059e2b805396e4b92342b49612062ef5e214b170f396fd9cab
Ethereum report:
Polygon reports:
As the proposal affects Aave v2 and v3 Polygon, 2 different payloads will get executed. So there are 2 different Aave Seatbelt reports, one per payload.
Aave v2 Polygon
Aave v3 Polygon
Like on every Aave cross-chain proposal, this one follows the procedure defined on https://github.com/bgd-labs/aave-v3-crosschain-listing-template. This means that after execution on Ethereum, the proposal payload (2 in this case) will be queued on the Polygon side of the cross-chain infrastructure and, after 1 day of timelock there, will be open for execution. Assuming that the cross-chain flow works properly, we have verified from a technical perspective that the payloads to be executed after timelock on Polygon do the following:
For Aave v2 Polygon:
- Calls
configureReserveAsCollateral()
on the Aave Pool Configurator for GHST, with the following changes:- Liquidation Threshold: 45% -> 40%
- Disabling borrowing
- The payload also introduces a disabling of borrowing for DPI, but this has no effect on Aave v2 Polygon, as DPI is already disabled.
For Aave v3 Polygon:
By calling setSupplyCap()
and setBorrowCap()
on the Pool Configurator, the following update of caps will be done:
- AAVE:
- Supply cap: 0 AAVE -> 36'820 AAVE
- BAL:
- Supply cap: 0 BAL -> 284'600 BAL
- Borrow cap: 0 BAL -> 96'798 BAL
- CRV:
- Supply cap: 0 CRV -> 937'700 CRV
- Borrow cap: 0 CRV -> 303'150 CRV
- DAI:
- Borrow cap: 0 DAI -> 3'860'000 DAI
- DPI:
- Supply cap: 0 DPI -> 1'417 DPI
- Borrow cap: 0 DPI -> 218 DPI
- EUR:
- Borrow cap: 0 EURS -> 728'520 EURS
- GHST:
- Supply cap: 0 GHST -> 5'876'000 GHST
- Borrow cap: 0 GHST -> 904'000 GHST
- LINK:
- Supply cap: 0 LINK -> 297'640 LINK
- Borrow cap: 0 LINK -> 51'029 LINK
- MAI:
- Borrow cap: 0 MAI -> 359'980 MAI
- WMATIC:
- Supply cap: 0 WMATIC -> 32'880'000 WMATIC
- Borrow cap: 0 WMATIC -> 9'225'000 WMATIC
- SUSHI:
- Supply cap: 0 SUSHI -> 299'320 SUSHI
- Borrow cap: 0 SUSHI -> 102'484 SUSHI
- USDC:
- Borrow cap: 0 USDC -> 30'680'000 USDC
- USDT:
- Borrow cap: 0 USDT -> 5'060'000 USDT
- WBTC:
- Supply cap: 0 WBTC -> 1'548 WBTC
- Borrow cap: 0 WBTC -> 155 WBTC
- WETH:
- Supply cap: 0 WETH -> 26'900 WETH
- Borrow cap: 0 WETH -> 2'690 WETH
✅ The code on the proposal payload corresponds to the proposal specification.
✅ The proposal includes a proper tests suite, checking all necessary post-conditions.
✅ BGD reviewed the payload before the proposal was submitted.
✅ Only one payload used via delegatecall
✅ BGD reviewed the procedure followed to submit the proposal.
✅ With BGD writing the payload, at least another party reviewed it.